The Basic Approach of __________ Requires That Lot-Sizing and Lot-Timing

Question 106

Multiple Choice

The basic approach of __________ requires that lot-sizing and lot-timing decisions be made first for the finished product so that sufficient finished products will be available to support the master production schedule.


A) material requirements planning
B) aggregate planning
C) long-term system design
D) master production scheduling
E) inventory management

Correct Answer:

verifed

Verified