As part of the controlling process, you have finished measuring the performance of your team. What must you do next?
A) Take corrective action.
B) Compare measured performance to standards.
C) Establish a unit of measure to gauge performance.
D) Modify past plans.
E) Restructure control systems and subsystems.
Correct Answer:
Verified