Solved

XYZ Company Uses Standard Costs for Allocating Costs to Work-In-Process

Question 39

Multiple Choice
XYZ Company uses standard costs for allocating costs to work-in-process and finished goods inventory.For the last few months,there have been high variances between total standard costs and actual costs.What is one of the likely reasons for this variance?
A)The accounting department has been developing the costs.
B)Production quantities are different than expected.
C)There is an increase in inventory quantities on hand.
D)The receiving department has been stockpiling raw materials.

XYZ Company uses standard costs for allocating costs to work-in-process and finished goods inventory.For the last few months,there have been high variances between total standard costs and actual costs.What is one of the likely reasons for this variance?


A) The accounting department has been developing the costs.
B) Production quantities are different than expected.
C) There is an increase in inventory quantities on hand.
D) The receiving department has been stockpiling raw materials.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents