What would be the estimated time for completion if time estimates for programming are as follows? optimistic = 4 weeks; pessimistic = 6 weeks; realistic = 5 weeks
A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
E) 30 weeks
Correct Answer:
Verified