You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units per eight-hour day. Task times and precedence relationships are shown in the table below.
a. Draw the precedence diagram.
b. Determine the desired cycle time.
c. Determine the theoretical minimum number of stations needed.
d. Balance this line using most following tasks.
e. What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q92: A work cell is scheduled to build
Q136: Explain what the purpose of assembly line
Q137: Consider the five ideas for determining the
Q139: What is the role of heuristics in
Q140: Define the following terms that occur in
Q142: An insurance claims processing center has
Q143: A company is designing a product
Q145: A facility is trying to set
Q146: Brandon's computer shop has hired a consultant
Q307: Assembly line balancing has just been used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents