Forward Scheduling

Question 21

Multiple Choice

Forward scheduling


A) begins with a delivery date, then offsets each operation one at a time, in reverse order
B) is well suited where the supplier is usually able to meet precise delivery dates
C) tends to minimize work-in-process inventory
D) assumes that procurement of material and operations start as soon as requirements are known
E) produces a schedule only if it meets the due date

Correct Answer: