A production line is to be designed for a job with three tasks. The task times are .4 minutes, 1.2 minutes, and .5 minutes. The maximum cycle time in minutes is:
A) .4.
B) .5.
C) 1.2.
D) 2.1.
E) .7.
Correct Answer:
Verified