A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product:
For output to equal projected demand, what is the theoretical minimum number of workstations needed?
A) 2
B) 2.8
C) 3
D) 4
E) 5
Correct Answer:
Verified
Q88: Heuristic rules are usually applied when
A)an optimum
Q95: The maximum allowable cycle time is computed
Q99: In the use of closeness ratings for
Q100: A company is designing a product layout
Q101: A company needs to rebalance a product
Q103: A company needs to locate three departments
Q104: A company needs to rebalance a product
Q105: The maker of the world-famous Chocolate Chip
Q106: A company needs to locate three departments
Q107: QRS Corp. is designing a product layout
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents