Available-to-promise in the first week is equal to beginning inventory plus MPS quantity, if any, less committed customer orders before the next MPS quantity.
Correct Answer:
Verified
Q21: Master schedulers are employed primarily by service
Q22: Aggregate planners attempt to balance
A)demand and inventories.
B)demand
Q23: A time fence in the master schedule
Q24: Subcontracting "in" would apply to periods in
Q25: Aggregate planning is capacity planning for
A)the long
Q27: Which of the following is an input
Q28: In the master production schedule, production is
Q29: Which one of the following is not
Q30: Which of the following would not be
Q31: After the first period of the planning