Which of the Following Is a Direct Input into Capacity

Question 32

Multiple Choice

Which of the following is a direct input into capacity requirements planning?
(I) the master production schedule
(II) routing information
(III) current shop loads
(IV) planned-order releases


A) II, III, and IV only
B) I, II, and IV only
C) I, III, and IV only
D) I and II only
E) I, II, III, and IV

Correct Answer: