
Consider the following work breakdown structure: 
What is the probability that this project will be completed within 130 days?
A) .8413
B) .90
C) .9544
D) .9772
E) .9987
Correct Answer:
Verified
Q86: Consider the following work breakdown structure:
Q87: Consider the following work breakdown structure:
Q88: A project is represented by the following
Q89: Consider the following work breakdown structure:
Q90: Consider the following work breakdown structure:
Q92: Consider the following work breakdown structure:
Q93: Consider the following work breakdown structure:
Q94: Consider the following work breakdown structure:
Q95: Consider the following work breakdown structure:
Q96: A project is represented by the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents