Why did the court find that the contract was frustrated in the case of: Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337?
A) Due to the declaration of war and the consequent impossibility of performing the contract.
B) Due to the non-occurrence of an event essential to achieve the substantial purpose of the contract.
C) Due to the fundamental and radical change in the circumstances of the contract.
D) Due to the complete destruction of the subject matter of the contract.
Correct Answer:
Verified
Q16: According to the case of Trident General
Q17: Which of the following is the best
Q18: An assignment of a debt at common
Q19: The absence of privity of contract will
Q20: A discharge by accord and satisfaction occurs
Q22: Which of the following is the best
Q23: The decision of the court in Fibrosa
Q24: What factors must be present in order
Q25: Describe the quantum meruit rule and when
Q26: The benefit of frustration is available in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents