Which of the following is NOT a true statement regarding Network diagrams?
A) All activities with a slack time equal to zero are on the critical path.
B) Nodes not on the critical path can be delayed (for some amount of time) without delaying the final completion of the project.
C) The latest expected completion time refers to the time in which an activity can be completed without delaying the project.
D) To construct a Network diagram, a horizontal bar is drawn for each activity that reflects its sequence and duration.
E) The critical path of a Network diagram is represented by the sequence of connected activities that produce the longest overall time period.
Correct Answer:
Verified
Q44: The phase of the project management process
Q55: A controlled process of initiating, planning, executing,
Q62: Which of the following states correctly the
Q71: Pessimistic time refers to:
A) the maximum period
Q79: A scheduling technique where the order and
Q80: A technique that uses optimistic, pessimistic, and
Q81: What would be the estimated time for
Q82: Which of the following slack times indicates
Q87: Slack time is equal to:
A) the difference
Q92: Which of the following refers to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents