If someone wants a system cheaply, quickly, and with a large scope, we can conclude:
A) That desire represents the three sides of the Project Triangle
B) This is normally not possible: you can usually only achieve two of those three objectives at a time.
C) Management might be providing an impossible goal.
D) All of the above
E) None of the above
Correct Answer:
Verified
Q34: Prototyping and RAD can be used to
Q35: All of the following are drawback of
Q36: The mantra for prototyping is "code a
Q37: Open source software is free but often
Q38: The maintenance and review phase is the
Q40: To support a common language and improve
Q41: Agile development tends to be _-oriented rather
Q42: Explain why IT projects are seen as
Q43: Two or more teams that work interdependently
Q44: _is the term used to describe what
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents