Abita Manufacturing has prepared the following flexible budget for October and it is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.
-The MOST LIKELY explanation of the above variances for Material A is that:
A) a lower price than expected was paid for Material A.
B) higher quality raw materials were used than were planned.
C) the company used a new supplier.
D) Material A used during October was $2,000 less than expected.
Correct Answer:
Verified
Q127: Explain what each of the following variances
Q128: In the beyond budgeting approach,targets are developed
Q129: _ occur(s)when managers ask subordinates to discuss
Q130: In the service sector,_ rather than machines
Q131: Zero-based budgeting requires that proponents of discretionary
Q133: What is the primary role of the
Q134: Grey Manufacturing has prepared the following flexible
Q135: Abita Manufacturing has prepared the following flexible
Q136: _ occur(s)when a superior simply tells subordinates
Q137: The actual information pertains to the month
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents