When using sampling for tests of controls,which of the following audit consequences may follow?
A) If sample results indicate that the control is operating effectively,but in fact it is not,control risk will be assessed too low.
B) If sample results indicate that the control is operating effectively,but in fact it is not,control risk will be assessed too high.
C) If sample results indicate that the control is not operating effectively,but in fact it is operating effectively,the audit is likely to be faulty because of reduced substantive tests.
D) If sample results indicate that the control is not operating effectively,but in fact it is operating effectively,control risk will be assessed too low.
Correct Answer:
Verified
Q22: Changing from a sampling plan using random
Q23: Which of the following may be used
Q24: The auditors expect a population deviation rate
Q25: In performing a test of a control
Q26: The 1,000 accounts receivable of Baker Company
Q28: If all other factors specified in an
Q29: Which of the following types of risk
Q30: A decrease in the tolerable misstatement has
Q31: The auditors expect a population deviation rate
Q32: Which of the following statistical sampling techniques
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents