Why is it necessary to consider the learning curve of resources on a project?
A) to estimate labor costs properly
B) to improve project team morale
C) because it always takes less time to do a task after someone has done it a few times
D) collective bargaining contracts require it
E) All of the above
Correct Answer:
Verified
Q1: Project budget is nothing more than the
Q5: Bottom-up budgets are usually more accurate in
Q10: Organizational tradition has little or no impact
Q13: With top-down budgeting, overlooking a small but
Q21: The best approach to handling change in
Q22: Mechanical tasks typically have higher learning rates
Q26: Random errors will tend to cancel out.
Q27: Qualitative risk analysis is not as important
Q29: A disaster is an event that may
Q31: Scenario analysis is not a popular technique
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents