Which of the following is not true regarding top-down budgeting?
A) It is based on the collective judgments of top and middle managers.
B) Overall project costs are estimated by top and middle managers and then passed on to the next lower level.
C) The overall budget cost is generally not very accurate.
D) Overlooking small but important tasks can lead to a serious budgetary problem.
E) All of the above are true concerning top-down budgeting.
Correct Answer:
Verified
Q47: A task is expected to take 20
Q54: Which of the following is not true
Q55: Reason for cost uncertainty in projects include;
A)
Q57: A problem with bottom-up budgeting is:
A) individual
Q61: Explain how budget uncertainly changes as the
Q61: Briefly explain how learning curves can help
Q63: Explain how you would use the shape
Q65: Briefly contrast the three different perspectives cost
Q68: Explain the concept of Brook's "mythical man
Q69: Risk management includes what three areas?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents