For which purpose is simulation NOT used with regard to project scheduling?
A) to overcome the limitations associated with statistical techniques used to develop probability of completion time estimates
B) to investigate the range of project completion times
C) to investigate the distribution of project completion times
D) to verify the accuracy of the optimistic, pessimistic and most likely time estimates
E) all of the above
Correct Answer:
Verified
Q6: The difference between LFT and EFT is
Q7: An event is a series of connected
Q15: Milestones are not depended upon the predecessor
Q33: The tasks of project planning, project budgeting,
Q36: What is project slack?
A) The amount of
Q39: What is it a milestone?
A) a significant
Q41: Why should we only draw the Gantt
Q42: Define the term Critical Path.
Q44: The simulation approach is generally preferred over
Q98: What is activity slack?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents