If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments, those payments would be called:
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Earned Value (EV)
E) None of these
Correct Answer:
Verified
Q26: A _ shows how the scope, features
Q27: The metric that provides an estimate of
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Q32: The budgeted cost of work scheduled for
Q33: Cost Variance (CV) is _
A) how much
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Q36: Barring a change in project scope and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents