Which of the following criteria can be included in scoring models for selecting projects?
A) potential profitability of the project
B) potential impact on the firm's competitive position
C) the organization's ability to market the output of a project
D) All of the above can be included
E) only a and b above
Correct Answer:
Verified
Q1: The project manager depends on legitimate authority
Q26: The comparative benefits method is considered a
Q31: Which of the following is not a
Q45: Which of the following is not a
Q46: Projects with deliverables that are incrementally different
Q52: R&D projects are oriented toward using newly
Q59: Scoring methods were developed to overcome some
Q60: One limitation of scoring methods is that
Q71: Ouroboros Construction started the construction of a
Q78: "Blue Sky" projects are…
A) R & D
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents