What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?
A) 3
B) 4
C) 4.3
D) 4.7
E) 7
Correct Answer:
Verified
Q90: Which type of precedence diagramming convention is
Q91: A task or set of tasks required
Q92: Which type of following precedence diagramming convention
Q93: An approximation of the variance for an
Q94: A series of connected activities (or intermediate
Q96: We can find the probability by finding
Q97: What is the standard deviation of a
Q98: What is activity slack?
Q99: Before this can be achieved or realized,
Q100: Formula for the expected completion time of