In earned value analysis…
A) it is desirable to have negative variances for both schedule and spending.
B) it is desirable to have positive variances for both schedule and spending.
C) the schedule variance should be positive and the spending variance negative.
D) the schedule variance should be negative and the spending variance positive.
E) ideally both variances would equal zero.
Correct Answer:
Verified
Q57: The plan-monitor-control cycle is best described as…
A)
Q58: In Agile, the product backlog and sprint
Q59: Control systems that make use of all
Q60: Control is one of the project manager's
Q61: The SPI is calculated as…
A) AC /
Q63: Estimated (remaining cost) to completion (ETC) is
Q64: Paulina, a fashion designer, has a new
Q65: Kimberley, a project manager in a software
Q66: The accountants of Junis Plex, a textile
Q67: The total cost to complete a task
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents