Identify the Statement That Is Not Correct Regarding a Project

Question 11

Multiple Choice

Identify the statement that is not correct regarding a project budget.


A) The budget is included in a project plan.
B) The budget is not an expression of organizational policy.
C) The budget serves as a control mechanism for the project.
D) The budget serves as a standard for comparison of planned and actual usage of resources.

Correct Answer:

verifed

Verified