A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a __________.
A) start to finish dependency
B) finish to start dependency
C) finish to finish dependency
D) start to start dependency
Correct Answer:
Verified
Q25: Project task E has the following estimates:
Q26: The shortest time in which the entire
Q27: Which of the following is not an
Q28: Project task E has the following estimates:
Q29: When using the beta distribution,the denominator of
Q31: The authors define _ as the time
Q32: A precedent relationship where the completion of
Q33: A project has three paths and a
Q34: Assume that task J has a most
Q35: _ law suggests that work expands to