If deterministic time estimates are used,and if project deadlines are firm,there is a high likelihood that it will __________.
A) not be necessary to crash any activities in projects
B) be necessary to crash the last few activities of most projects
C) be completed on time and within budget
D) be completed as per schedule
Correct Answer:
Verified
Q10: When crashing a project,our first task is
Q11: If the crash cost is $2,500,the normal
Q12: A project task is said to be
Q13: The use of _ activity time estimates
Q14: If the crash cost is $2,500,the normal
Q16: In CPM,_ are specified.
A)exact levels of uncertainty
Q17: The points between the extreme points of
Q18: The standard practice with AOA and AON
Q19: Fast-tracking is a partial use of the
Q20: _ itself is always a critical resource