Solved

Which of the Following Effects Will Be Observed in a Network

Question 14

Multiple Choice

Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?


A) Each activity will make use of all the slack available to it.
B) The network will not have any critical activities.
C) It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D) Many of the activities will be scheduled prior to the start date of the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents