Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?
A) Each activity will make use of all the slack available to it.
B) The network will not have any critical activities.
C) It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D) Many of the activities will be scheduled prior to the start date of the project.
Correct Answer:
Verified
Q10: The _ technique overlaps the design and
Q15: If deterministic time estimates are used,and if
Q21: The _ heuristic provides a general solution
Q22: The usual purpose of the _ scheduling
Q24: One of the problems that Goldratt observed
Q26: The _ approach to constrained resource scheduling
Q30: Most heuristic solution methods start with the
Q31: If a contradiction or conflict between constraints
Q34: The methods to find an optimal solution
Q38: The tasks that logically precede a particular
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents