If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
Correct Answer:
Verified
Q14: Which of the following effects will be
Q15: If deterministic time estimates are used,and if
Q17: One of the problems that Goldratt observed
Q22: The use of _ activity time estimates
Q23: Three important parameters used to assess the
Q24: When we change technology, we may also
Q25: Given W = D * U for
Q26: The _ approach to constrained resource scheduling
Q26: _ times result from an attempt to
Q34: The methods to find an optimal solution
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents