The main planning tasks performed as part of project scope management include scope planning,scope definition,and ____.
A) scope evaluation
B) scope reduction
C) creating the WBS
D) scope expansion
Correct Answer:
Verified
Q18: The project charter,preliminary scope statement,and current project
Q19: Work that is not included in the
Q20: Every item on a WBS needs to
Q21: There can be more than one critical
Q22: The precedence diagramming method uses only finish-to-start
Q24: After you determine the reason for a
Q25: Duration relates to the time estimate,not the
Q26: The main purpose of project planning is
Q27: The critical path is the shortest path
Q28: The main output of scope planning is