The main disadvantage of ____ is that it can end up lengthening the project schedule,because starting some tasks too soon often increases project risk and results in rework.
A) reviewing
B) crashing
C) extending
D) fast tracking
Correct Answer:
Verified
Q60: _ includes the actual amount of time
Q61: The approved project scope statement and its
Q62: You need to plan the project _
Q63: A work _ is a task at
Q64: Project _ management involves defining and controlling
Q66: Project _ management includes the processes required
Q67: _ estimates,also called top-down estimates,use the actual
Q68: _ is a technique for making cost
Q69: A(n)_ is a deliverable-oriented grouping of the
Q70: A WBS _ is a document that