Given the Earned Value and ____,You Can See How Well

Question 48

Multiple Choice

Given the earned value and ____,you can see how well the project team is meeting schedule goals and forecast when the project will be completed based on past schedule performance.


A) actual cost
B) cost variance
C) planned value
D) schedule variance

Correct Answer: