_____ are the starting point for actual use of MRP,and the varieties are consequently instructive.
A) BOMs
B) MTSs
C) MTOs
D) ATOs
Correct Answer:
Verified
Q72: The first step in the planning hierarchy
Q73: DRP1 can be defined as
A)determining the needs
Q74: In a _ environment,there is some latitude
Q75: _ is a higher order planning system
Q76: _ uses the principle that the lowest
Q78: _ is among the simplest ordering methods,but
Q79: Gross requirements less the projected stock-on-hand,at time
Q80: For the example in the text (see
Q81: MRPII is responsive to the strategic business
Q82: The essence of MRP II is
A)feedback planning