A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:
A) CPM addresses the risk associated with duration estimates whereas PERT does not.
B) unlike CPM, PERT estimates only when there is no risk of uncertainty.
C) CPM involves more work than PERT because it requires several duration estimates.
D) PERT uses different duration estimates whereas CPM uses one specific duration estimate.
Correct Answer:
Verified
Q52: The critical path is the _ path
Q57: The amount of time an activity can
Q59: Which of the following is true of
Q60: Which of the following dependencies involve relationships
Q61: In the activity defining process, the project
Q63: The technique for making cost and schedule
Q64: In project time management, the process of
Q65: _ states that work expands to fill
Q66: Which of the following techniques involve doing
Q67: Which of the following is an output
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents