The earliest finish time is the total of the earliest start time and the activity duration.
Correct Answer:
Verified
Q10: In PDM,an activity can have predecessors with
Q11: Project Evaluation and Review Technique is a
Q12: In PDM,a project will have one start
Q13: A work breakdown flowchart is useful for
Q14: Causing a delay to the whole project
Q16: Free float is an early warning and
Q17: Primary advantages of PERT are that it
Q18: If the early start for an activity
Q19: SAP PS is a free,web-based project software
Q20: When making a forward pass through a