Dependencies involving relationships between the project and non-project activities best defines
A) mandatory dependencies.
B) external dependencies.
C) discretionary dependencies.
D) internal dependencies.
Correct Answer:
Verified
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity
Q58: Basic reasons for creating dependencies of project
Q59: If prototype testing can be started only
Q61: A method of planning and managing projects
Q62: Which of the following includes activities performed
Q63: Shortening an activity is called
A)float.
B)crash.
C)reduction.
D)smoothing.
Q64: The ratio of rise and run of
Q65: If the optimistic time is 3,the most