The shortest time in which an activity can be completed best defines
A) realistic time.
B) optimistic time.
C) pessimistic time.
D) designated time.
Correct Answer:
Verified
Q49: Which of the following is used in
Q50: When constructing the PDM,an activity can have
A)predecessors
Q51: Which of the following usually occurs when
Q52: A specific task,or set of tasks,that is
Q53: When working with project management software,factors that
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity
Q58: Basic reasons for creating dependencies of project
Q59: If prototype testing can be started only