Deviation from an original plan best defines
A) scope deviation.
B) variance.
C) design creep.
D) silver bullet syndrome.
Correct Answer:
Verified
Q36: Which of the following focuses on identifying
Q37: A process of tracking,reviewing,and regulating the progress
Q38: The process of managing change in hardware,software,documentation,and
Q39: Resource leveling extends the project time and
Q40: The costs of materials that are entirely
Q42: A potential benefit given up when one
Q43: Which of the following prepares a detailed
Q44: Which of the following provides a rough
Q45: Which of the following compares schedule deviations
Q46: Which of the following uses "work in