In Hadley v.Baxendale,when Hadley sued because Baxendale took unnecessary time to get a crankshaft repaired,causing Hadley's mill to close for an extended time,the court found
A) Baxendale owed Hadley compensatory damages because the mill was shut down for an extended time directly as a result of Baxendale's delayed delivery.
B) Baxendale owed Hadley consequential damages because the mill was shut down for an extended time as a result of Baxendale's delayed delivery and the shutdown was a foreseeable indirect result of Baxendale's delay.
C) Baxendale did not owe Hadley consequential damages because the extended closing time was not foreseeable despite Baxendale's delay in delivery.
D) Baxendale did not owe Hadley either compensatory or consequential damages but did owe punitive damages due to the unreasonable delay in delivery.
Correct Answer:
Verified
Q65: Which of the following is not an
Q66: Damages intended to punish a wrongdoer are
Q67: In what way do legal remedies and
Q68: In which of the following scenarios would
Q69: When Olivia was a senior in high
Q71: Mark is an accounting major at a
Q72: Josh entered into a contract with Donna
Q73: Which of the following is rarely awarded
Q74: Amos owns a piece of land along
Q75: When examining and enforcing conditions precedent and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents