Creating a Realistic Schedule Is Often an Iterative Process Because

Question 34

Multiple Choice

Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:​ 


A)  Logical order 
B)  Imposed dates 
C)  Resource availability 
D)  Quality metrics

Correct Answer:

verifed

Verified