Multiple Choice
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data provided in Figure 7-6.Which activities constitute the critical path for this project network?
A) A-D-F-I
B) A-C-E-H-I
C) A-B-E-H-I
D) A-B-E-G-I
Correct Answer:
Verified