When Estimating Resource Needs,project Teams Should Consider All the Following

Question 35

Multiple Choice

When estimating resource needs,project teams should consider all the following EXCEPT:​ 


A)  support needs such as information systems and other services. 
B)  the time required to communicate between activities. 
C)  issues involved in securing specific knowledge or skills that are required. 
D)  strengths and weaknesses of scoring models.