Figure 8-2 Software Programmer Loading Chart

Question 28

Multiple Choice

  Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2.What percent of available time is the software programmer assigned to work activities on Thursday?​  A)  80 percent  B)  100 percent  C)  150 percent  D)  200 percent Figure 8-2 Software Programmer Loading Chart
-Consider the software programmer loading chart presented in Figure 8-2.What percent of available time is the software programmer assigned to work activities on Thursday?​ 


A)  80 percent 
B)  100 percent 
C)  150 percent 
D)  200 percent