Multiple Choice
Figure 8-2 Software Programmer Loading Chart
-Consider the software programmer loading chart presented in Figure 8-2.What percent of available time is the software programmer assigned to work activities on Thursday?
A) 80 percent
B) 100 percent
C) 150 percent
D) 200 percent
Correct Answer:
Verified