All of the following factors must be in place in order to develop an analogous estimate effectively EXCEPT:
A) An organization must know details behind the time value of money.
B) An organization must know how and to what extent the proposed project differs from the previous project.
C) An organization must have experience in performing similar projects.
D) An organization must know how much previous projects actually cost.
Correct Answer:
Verified
Q26: Value engineering is aimed at increasing the
Q27: Projects often include indirect costs that are
Q28: Which estimating technique decomposes the work into
Q29: Which estimating technique uses a statistical relationship
Q30: Costs that repeat as project work continues
Q32: Activity based costing allocates overhead (indirect costs)to
Q33: What type of cost is incurred when
Q34: Complex projects such as research and development
Q35: Vendor bid analysis is used to determine
Q36: The cost management plan provides guidelines to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents