Occasionally,organizations Will Approve Projects That Are Forecast to Lose Money

Question 23

Multiple Choice

Occasionally,organizations will approve projects that are forecast to lose money when fully costed and sometimes even when only direct costed.Which of the following is not a good reason for doing this.


A) Acquire knowledge concerning a specific or new technology
B) Get the organization's "foot in the door"
C) Improve their competitive position
D) They plan on cutting corners on work and material,or forcing subsequent contract changes to make up the cost

Correct Answer:

verifed