Identify the statement that is not a major advantage of placing a project in the matrix approach.
A) A single individual,the project manager,takes responsibility for managing the project.
B) The project will have access to representatives from the administrative units of the parent firm.
C) The division of authority between the project manager and the functional managers is complex.
D) There may be less anxiety among team members about what will happen to them when the project is completed.
Correct Answer:
Verified
Q1: Viewing the whole at one time rather
Q2: The _ matrix is most similar to
Q3: There are many reasons for the rapid
Q4: Which organizational structure has the highest availability
Q6: Identify the statement that is not a
Q7: When a project requires the integration of
Q8: Identify the statement that is not a
Q9: A major advantage of using a _
Q10: The _ matrix is least similar to
Q11: The _ organizational form is a pure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents