Once the Project Charter Is Completed and the Project Approved,a

Question 3

Multiple Choice

Once the project charter is completed and the project approved,a more detailed project plan can be developed.Which of the following issues is not addressed in the detailed project plan?


A) The process for managing change
B) The salary for the project manager
C) A plan for communicating with and managing stakeholders
D) Establishing the cost baseline for the project

Correct Answer: