You have been asked to estimate the costs for a project to build an industrial power plant.Based on historical data,the steam turbine accounts for 30 percent of the total costs for the plant.If the steam turbine costs $300,000,the expected top-down estimated cost for this project would be __________.
A) $10,000
B) $100,000
C) $900,000
D) $1,000,000
Correct Answer:
Verified
Q1: If a project budget is underfunded,it will
Q2: A budget strategy that is based on
Q3: Unless the project manager is familiar with
Q5: Many lower-level managers often treat the entire
Q6: If a project budget is over funded,it
Q7: The advantage of the_ process is that
Q8: In order to develop a budget,the project
Q9: The Pathfinder Mission was to go where?
A)The
Q10: The _ form of budgeting has the
Q11: Identify the statement that is not correct
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents