A work element in the project plan requires 50 hours of labor each by four carpenters.The carpenters are paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges.Based on this data,the appropriate total cost is __________.
A) $2,400
B) $3,000
C) $4,600
D) $5,400
Correct Answer:
Verified
Q10: The _ form of budgeting has the
Q11: Identify the statement that is not correct
Q12: A work element whose cost is fully
Q13: The project's budget should _.
A)associate resource use
Q14: _ is a plan for allocating resources.The
Q16: The pattern of constraints in a budget
Q17: The _ charge is composed of the
Q18: _ relies on well-known statistical correlations between
Q19: _ are where the defined responses to
Q20: Unknown unknowns are not part of the