A project has three paths and a desired completion time of 43 days.The first path has a 70 percent probability of being completed in 43 days.The second has an 85 percent probability and the third haws a 90 percent probability.What is the probability that the project will be completed on time?
A) 53.55 percent
B) 70 percent
C) 90 percent
D) 99.55 percent
Correct Answer:
Verified
Q28: Project task E has the following estimates:
Q29: When using the beta distribution,the denominator of
Q30: A precedence relationship where the completion of
Q31: The authors define _ as the time
Q32: A precedent relationship where the completion of
Q34: Assume that task J has a most
Q35: _ law suggests that work expands to
Q36: _ have a weakness of being difficult
Q37: It is important to good project management
Q38: The calculation of the standard deviation for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents