Solved

A Project Has Three Paths and a Desired Completion Time

Question 33

Multiple Choice

A project has three paths and a desired completion time of 43 days.The first path has a 70 percent probability of being completed in 43 days.The second has an 85 percent probability and the third haws a 90 percent probability.What is the probability that the project will be completed on time?


A) 53.55 percent
B) 70 percent
C) 90 percent
D) 99.55 percent

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents