The formula for computing the cost / time slope for each activity that can be crashed is __________.
A) (crash cost + normal cost) / (crash time + normal time)
B) (crash cost - normal cost) / (crash time - normal time)
C) (normal cost + crash cost) / (normal time + crash time)
D) (normal cost - crash cost) / (normal time - crash time)
Correct Answer:
Verified
Q1: The two principles to follow when crashing
Q3: When we change technology,we may also be
Q4: One cannot save _,rather one can only
Q5: If the crash cost is $1,000,the normal
Q6: The _ technique overlaps the design and
Q7: Economically speaking,crashing a project creates a technology
Q8: _ describes the amounts of individual resources
Q9: _ times result from an attempt to
Q10: When crashing a project,our first task is
Q11: If the crash cost is $2,500,the normal
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents